Tesla testing and commissioning provides services that promote long-term, efficient operation of electrical systems. We mobilize teams to all parts of the Saudi Arabia, servicing power delivery systems from 480V to 380 kV.
Acceptance Testing
Acceptance testing determines that each piece of electrical equipment is ready for energization and that it will operate as designed and perform as an integral part of the system. Test personnel inspect and provide acceptance testing on each piece of the equipment to verify it meets specification to, energize and verify the overall installation of the system conforms to the drawings.
Energization
Once our team determines that individual pieces of equipment are operating properly, our testing engineers develop an energization plan. We energize the entire system to verify it is operating as intended and meeting design requirements. Our clients receive full documentation of the system’s performance and integrity.
Tesla team has the Capability to carry out the following testing Scope on various electrical substations up to 380 KV :
HV/MV/LV Swithcgear
- Pre-Commissiong
- Equipments testing
- CT & VT Testing
- Meters & Transducers testing
- Relays testing
- function & scheme check
- stability test
Protection & Control Panels
- Pre-Commissiong
- Aux.Relays testing
- Back up relays testing
- Main Relays Testing
Protection Modification work
- Carrying out Complicated Modification of Existing protection scheme
- Reproduction of Existing Schematics
- Dismantling of existing panel then mounting and wiring of new equipments
Tesla team has the Capability to carry out the following main relays acceptance and final testing on various electrical substations
SIEMENS
- Line protection : 7SA6 , 7SD5 ....etc
- Transformer Differntial : 7UT6,7UT5.....etc
- BB Differntial : 7SS
- Back up relays : 7SJ...etc
AREVA
- Line protection : P443 , P546...etc
- Transformer Differntial : P633.....etc
- BB Differntial : P740
- Back up relays : P142...etc
ABB
- Line protection : REL6,RED6....etc
- Transformer Differntial : RET6.....etc
- BB Differntial : REB500
- Back up relays : REJ525...etc
SEL
- Line protection : SEL 421
- Transformer Protection : SEL387,487E
- Feeder Protection: SEL751,SEL451
- Capcitor Prot. : SEL487V
- Motor Protection : SEL710
GE
- Back up prot. : C60
- Capcitor Prot. : C70